Mominpura Y-Shaped Flyover Finally Picks Up Speed — 70% Done, March 2027 Target Set After Years of Delays

Published: May 23, 2026 | Category: Nagpur Local | By: Nagpur Updates Desk
After years of frustrating delays, Nagpur’s long-awaited Mominpura Y-shaped flyover is finally moving at pace.
The Maharashtra Rail Infrastructure Development Corporation (MRIDC) has confirmed that 70% of the project work is now complete. Construction is progressing steadily across multiple sections. And after clearing the major hurdles that stalled the project for years, MRIDC has set a revised completion target of March 2027.
For commuters battling chronic congestion between Kadbi Chowk and Golibar Chowk — one of Nagpur’s most congested stretches — this is genuinely encouraging news.
What Has Been Completed So Far
MRIDC officials have provided a detailed progress update. Here is where things stand:
- Foundation and substructure work — fully complete
- Superstructure work including girder launching — approximately 50% done
- Road concretisation beneath the flyover — work has started
- Overall project completion — 70%
The pace of work has accelerated significantly after most of the major encroachment and land-related obstacles were cleared. Officials confirmed that construction is now progressing steadily across all active sections of the project.
The Flyover: Design, Route and Scale
The Mominpura flyover is not a standard straight-line elevated road. Its Y-shaped design makes it one of the more complex urban flyover projects in Nagpur.
The flyover originates at Kadbi Chowk and extends 2.82 kilometres to the Pehelwan Shah Dargah T-point. From there, it branches into two arms:
- First arm — towards Mominpura — with an 11-metre-wide carriageway
- Second arm — towards Santra Market, connecting to the Platform No. 8 side of Nagpur Railway Station
This Y-shaped design serves a dual purpose. It simultaneously relieves congestion on the Mominpura stretch and provides a direct elevated link towards Santra Market and the railway station — two of central Nagpur’s busiest destinations.
Once operational, the flyover will significantly cut travel times through one of the city’s most chronically congested corridors — especially near the busy Motibagh railway crossing area.
The Cost: ₹146 Crore Became ₹185 Crore
The financial story of this project is a cautionary tale about what delays cost.
The flyover was originally approved at ₹146 crore. Due to the years of delays — caused by encroachments, land disputes, local resistance, tree-felling permissions, and utility shifting — the project cost has now escalated to approximately ₹185 crore. That is an increase of nearly ₹39 crore — money that was never in the original budget and has been added purely as a consequence of delayed execution.
This cost escalation is not unusual for infrastructure projects that face significant implementation delays. But it is a stark reminder that the years of encroachment disputes and local resistance at Mominpura did not just delay traffic relief — they cost Nagpur’s taxpayers tens of crores of additional public money.
What Caused Years of Delay?
The Mominpura flyover’s troubled history reflects the complex reality of urban infrastructure development in densely populated areas.
Encroachments were the biggest problem. The Mominpura area has significant commercial activity and residential density. Many structures — shops, residential buildings, and unauthorised extensions — were in the path of the flyover alignment. Getting these removed required a combination of legal processes, negotiations, and in some cases, forceful action.
We recently reported on the NMC’s anti-encroachment drive in Mominpura — where Corporator Wasim Khan climbed atop a JCB to protest the drive. That incident illustrates how politically and socially charged encroachment removal in this area can be.
Local resistance added to encroachment challenges. Residents and shopkeepers affected by the flyover construction raised objections at multiple points — slowing the legal and administrative processes needed to clear the way.
Land acquisition disputes required resolution through official channels — adding months to the timeline.
Tree-felling permissions had to be secured from forest and environment authorities — another layer of regulatory clearance that took time.
Utility shifting — moving electricity cables, water pipelines, and other underground infrastructure out of the construction zone — proved more complex and time-consuming than anticipated.
Officials confirmed that most of these hurdles have now been resolved — which is why the pace of construction has finally accelerated to the point where 70% completion has been achieved.
What Remains: The Final 30%
With 70% done, the remaining work includes:
- Completion of the remaining 50% of superstructure and girder work
- Full completion of road concretisation beneath the flyover
- Installation of safety barriers, lighting, and signage
- Approach ramp construction and finishing works at both arms of the Y
- Final traffic management and signalling integration at Kadbi Chowk and the Pehelwan Shah Dargah T-point
The March 2027 deadline gives MRIDC approximately 10 months to complete this remaining work. At the current accelerated pace, this appears achievable — provided no new obstacles emerge.
What the Flyover Will Mean for Nagpur
The Mominpura Y-shaped flyover will deliver meaningful relief to one of Nagpur’s most congested urban corridors.
Kadbi Chowk to Golibar Chowk is notorious for traffic gridlock — particularly during peak morning and evening hours. The high density of commercial activity in the Mominpura, Santra Market, and railway station areas means that road-level traffic in this zone is perpetually heavy.
An elevated corridor that takes a significant volume of through-traffic above the road level will dramatically reduce surface congestion. Commuters heading from Central Nagpur towards Mominpura or the railway station will be able to bypass the worst bottlenecks entirely.
This is part of a broader pattern of flyover-led traffic relief that Nagpur is experiencing across the city. The Indora–Dighori flyover corridor — featuring the iconic Ashoka Stambh at Ashok Square — is due to be inaugurated in June 2026. The Mominpura flyover, when complete in March 2027, will add another critical elevated link to Nagpur’s rapidly expanding road network.
March 2027: Cautious Optimism
The March 2027 target deserves to be treated with cautious optimism — not blind confidence.
This project has missed deadlines before. The encroachment-driven delays that pushed the cost from ₹146 crore to ₹185 crore were not anticipated when the project was first approved. And in Nagpur’s infrastructure landscape, unforeseen obstacles have a habit of appearing just when momentum builds.
However, the current ground situation — 70% complete, major obstacles cleared, active construction across multiple sections — is genuinely more encouraging than at any previous point in this project’s history.
If MRIDC maintains this pace, Nagpur commuters may finally have reason to celebrate in March 2027.
Nagpur Updates will track construction progress on the Mominpura flyover and alert you to any changes in the March 2027 target as the project moves forward.
Tags: Mominpura Flyover, MRIDC Nagpur, Y-Shaped Flyover, Kadbi Chowk, Nagpur Infrastructure, Nagpur Traffic, Santra Market Nagpur, Nagpur Local News 2026



